Bathurst adopts a $94 million walking and cycling network with no money attached yet: CBD crossings come first, and CBD bike lanes drop to last over parking and cost
On Wednesday 21 October Bathurst Regional Council adopted its Active Transport Strategy, six votes to two. The core network of footpaths, shared paths and cycleways is costed at about $94 million, and the resolution commits no money to it: funding goes to the budget process for 2027/28 and beyond. The strategy ranks $3.4 million of CBD pedestrian upgrades, chiefly raised crossings, first and the dearest link, $24.8 million of CBD cycleways, last, citing its cost and objections to losing parking. A separate review is looking at a 30 km/h limit for the CBD.
What the council adopted
The Bathurst Region Active Transport Strategy was written by Bitzios Consulting, with a Transport for NSW grant under its Get NSW Active program covering 75 per cent of the cost of preparing it. It builds on the council's Community Access and Cycling Plan of 2011 and becomes the main document for deciding which footpaths, shared paths and cycleways get built first. Alongside it the council adopted three engineering documents: two reports on applying the state's Design of Roads and Streets guide to new and existing suburbs, and an urban road network plan that classifies every urban street and sets a desired future speed for each.
The resolution, moved by Cr E West and seconded by Cr J Underwood, also starts an amendment to the council's development control plan and engineering guidelines, so the new footpath and cycleway standards become conditions on development. Staff name Laffing Waters as a future greenfield subdivision that will be held to them. The Mayor, Cr B Fry, and Crs R Taylor, West, Underwood, N Packham and S Wright voted for it; Crs W Aubin and T Gullifer voted against. Cr N Cranston was absent.
The draft was on exhibition from 24 August to 21 September and drew 27 submissions. Staff describe most as generally supportive, and made three changes: one route reclassified, one path relabelled as pedestrian only, and an allowance added for widening bridges and culverts.
The order, and the bill
The strategy ranks 13 links. Its own costing table, in 2025 dollars, puts a price and an indicative funding timeline on each:
| Rank | Link | Cost | Timeline |
|---|---|---|---|
| 1 | CBD pedestrian upgrades | $3,387,140 | Short term (0 to 1 year) |
| 2 | CBD surrounds | $16,630,525 | Medium term (1 to 4 years) |
| 3 | Kelso to CBD | $11,142,580 | Medium term (4 to 6 years) |
| 4 | Eglinton to CBD | $5,419,570 | Medium term (6 to 7 years) |
| 5 | West Bathurst to CBD | $3,123,230 | Long term (more than 7 years) |
| 6 | South Bathurst to CBD | $7,632,880 | Long term |
| 7 | Llanarth to CBD | $4,781,695 | Long term |
| 8 | Windradyne to CBD | $3,376,660 | Long term |
| 9 | Kelso to CBD off-road paths | $4,020,975 | Long term |
| 10 | Laffing Waters to Kelso | $4,228,760 | Long term |
| 11 | Windradyne to Llanarth | $4,171,200 | Long term |
| 12 | North Kelso | $2,106,910 | Long term |
| 13 | CBD cyclist upgrades | $24,821,960 | Long term |
The 13 links add up to $94,844,085, and the strategy recommends another $5 million for culvert
widening across the network. The staff report, citing the strategy, is plain about the scale: it is unlikely that Council will be able to implement all recommendations in the short to medium term
.
It says talks with Transport for NSW point to the council being able to apply for up to
$5 million a year for key projects over the next seven years.
Why the CBD bike lanes fell to last
The ranking changed after the consultant's detailed appraisal. CBD pedestrian upgrades rose
from third to first, on very positive community feedback and the number of people on foot in the
CBD. Kelso to the CBD, along the heavily used River Walk, fell from first to third. CBD cyclist
upgrades fell furthest, from eighth to thirteenth. The appraisal records significant community push back regarding removal of car parking spaces
in the CBD to make room for cycling connections, and judges the link Not expected to be feasible in the short term from a construction and community support perspective
.
It adds that the council could bring the work forward if community attitudes change.
The CBD speed limit is a separate decision
Bathurst is one of the councils Transport for NSW invited into its Regional Local Government Speed Partnership, and it nominated the CBD. That review covers the area bounded by Rankin, Piper, Bentinck and Durham streets, plus six streets, or stretches of them, that the strategy proposes as quiet cycling routes: Seymour, Lambert, Keppel, Charlotte, Elizabeth and Stanley. It is considering a signposted 30 km/h limit with raised pedestrian crossings to support it, introduced in stages as funding allows. The road network plan also identifies some civic spaces as possible 10 km/h shared zones.
The exhibition material gives the case. There were seven serious injury crashes from 2020 to
2024 where the changes are proposed, one involving a pedestrian and four involving cyclists, and
it says current operating speeds in parts of the area are between 30 and 40 km/h, already close to the proposed limit
.
Two submissions objected to lowering the limit; staff note that more submissions favoured the
reduction than opposed it. Staff answered that over 500 metres the change
from 50 to 30 km/h would add 24 seconds of travel time
.
The resolution did not change the speed limit, though the road network plan it adopted names
30 km/h as the preferred future speed environment for the CBD. Staff expect the review to come back to council
separately.
Our view
This is opinion, built on the facts above. Putting the cheapest, most supported link first is sensible: $3.4 million of CBD pedestrian upgrades helps the most people, and the raised crossings the strategy recommends also support the slower streets the speed review is after. But a strategy adopted with no money committed is a list. The arithmetic is tight even on the hopeful case. The four links the strategy times within seven years cost $36.6 million. If Bathurst won the most staff say Transport for NSW has signalled, $5 million every year for seven years, that is $35 million, before the council finds a dollar of its own. Everything after fourth place, including the CBD cycleways, carries only the strategy's long-term label of more than seven years.
Dropping those cycleways to last is mainly a choice about parking, on top of a $24.8 million price, and the strategy says so. That is a legitimate call for a council to make, but it should be revisited with the speed review's crash figures in view: four of the seven serious injury crashes in the review area involved cyclists. The real test of this vote is the 2027/28 budget.
When the draft 2027/28 budget is published, we will report what it sets aside for the strategy. When the CBD speed limit review comes back to council, we will report what it recommends.
How we sourced this
We read item 9.2.5 in the minutes of Bathurst Regional Council's ordinary meeting of 21 October 2026, which reproduce the staff report, the response to submissions and the resolution with its division (minutes pages 60 to 73). We also read the item's attachments in the business paper for that meeting: the final strategy (its Tables 11.5, 11.6 and 19.1) and the CBD speed limit review exhibition material. The $36.6 million and the $35 million are our arithmetic on the council's figures. We checked the 13 link costs add to the $94,844,085 total. We have not read the 27 submissions individually, the concept plans, which were too large to attach to the report, or the two engineering reports in detail, and we have not contacted the council. The section headed Our view is opinion.
Sources
Made like this: AI did the reading and drafting, people carry the responsibility, working from the primary sources below. Before it ran, a script matched 5 quotations letter for letter against our saved copies. More on our method.
- Bathurst Regional Council, Minutes of the Ordinary Meeting of Council, 21 October 2026, item 9.2.5, Adoption of Draft Bathurst Region Active Transport Plan and Associated Road Design Policies (PDF, pages 60 to 73, read 23 October 2026): the summary, the exhibition and submissions, the response to the speed limit objections, the $94 million and Transport for NSW funding, resolution ORD2026-273 and the division.
- Bathurst Regional Council, Business paper, 21 October 2026, item 9.2.5 with attachments (PDF, 69 MB, read 23 October 2026): the final strategy's Tables 11.5 and 11.6 (page 94) and Table 19.1 (page 121), and the CBD speed limit review exhibition material (pages 301 to 303).