Bathurst's $300,000 finance review: the 21 October papers say both that nothing has been spent and that about 70 per cent has
Bathurst Regional Council asked for a monthly public report on its
Ernst & Young Parthenon financial sustainability review, including what it has cost
against the $300,000 set aside. The report going to the meeting on
21 October gives two answers. One sentence reads There has been no expenditure incurred to date.
The financial implications section reads Expenditure to date of approximately 70% of the budget.
A month ago, the same report said nothing had been paid.
Updated 13 November 2026. The business paper
for the 18 November meeting carries this month’s update, item 9.2.13. The sentence saying
no expenditure had been incurred is gone. The only figure left is Expenditure to date of approximately 70% of the budget.
The report does not say the earlier sentence was wrong, or whether the 70 per cent is money
paid, invoiced or committed. The final Ernst & Young report, which the October paper
expected in November, is not on the agenda. Its status now reads EY are finalising the report to be tabled at a future Council Meeting.
The recommendation is again only to note the information, with a recorded vote. We will read
the 18 November minutes and report anything councillors are told beyond the paper. Source 5.
Updated 23 October 2026. The minutes of the
21 October meeting are out. They reproduce the report unchanged, still saying both There has been no expenditure incurred to date.
and Expenditure to date of approximately 70% of the budget.
Councillors resolved only to note the information, eight votes to none (resolution
ORD2026-283, Cr Cranston absent). The minutes record no amendment and no explanation of which
figure is right. Source 4.
Updated 21 October 2026. We had not read the February 2026 report behind the review. We have now read it and the minutes of that meeting, and added a paragraph on who added the monthly reporting duty, changed two sentences in how we sourced this, added a source entry and updated the source count. Nothing else has changed.
What the review is and why the money is reported monthly
On 18 February 2026 the council endorsed a Financial Sustainability Strategy called
Beyond 2026 and set aside $300,000 for external consultants to run an options analysis,
to evaluate an SRV to be included as one of the options
, and to consult the community on
every option that came out of it. An SRV is a special rate variation: permission from the
state pricing regulator, IPART, to raise its general rate income above the annual rate peg. The same resolution
required monthly public reporting to Council on the progress of the consultancy engagement(s) including expenditures to date against the approved allocations
.
Ernst & Young Parthenon has the engagement; the report also describes a
Pathway to Sustainability review
assessing the council's finances and operations
against external benchmarks.
The February minutes show the monthly reporting duty was added by councillors and was not in the general manager’s recommendation. The report recommended the $300,000, which it gave as GST exclusive, and a further report, but no monthly reporting. An amendment moved by Cr S Wright and seconded by Cr N Cranston added it, with two other conditions: that councillors see the consultancy’s scope of works before any procurement documents were released, and the final brief or tender documents before they were issued. The amendment carried six votes to three, and the resolution, ORD2026-31, then carried seven to two.
So the monthly item has one figure it exists to give, and this month it gives it twice, differently.
What changed between September and October
The update in the 16 September minutes (item 8.3.7) was consistent with itself. Its body
said There has been no expenditure incurred to date.
Its financial implications section said Expenditure to date is 0% of the budget, no payments have been made by Council for this consultancy project at this date.
In the October report (item 8.3.8), the body sentence is the same, word for word. The financial implications line is the part that changed, to about 70 per cent. On a $300,000 allocation that would be about $210,000 (our arithmetic). The report does not say which statement is current, or whether the 70 per cent is money paid, invoiced or committed. Both reports also note that because the budget was not spent by 30 June 2026, it is being carried over into this financial year.
Where the review is up to
The September report said Ernst & Young presented its draft findings to councillors
at a briefing on 24 August 2026, and that the council had begun reviewing the operational
opportunities identified in the draft. The October report says the council
continues reviewing the operational opportunities identified through the draft EY report
,
that Ernst & Young is preparing the final report with consideration of any councillor
feedback from the last strategy session, and that the full final report will go to a council meeting when Ernst
& Young finishes it, which the report expects in November 2026. In September that
was later this year
.
Both reports say The final report will be made available to the community as we consult on the path forward.
Neither says the draft will be published. The recommendation for 21 October is only that
council notes the information, with a recorded vote.
The review sits against the council's own draft 2025/26 accounts, which we covered on 8 October: a positive operating result that included $12.75 million of land and asset sale gains, a general fund the council's report says is still in underlying deficit, and road renewal spending down from $9.8 million to $1.1 million.
Our view, labelled as such. The council required monthly public reporting on a consultancy whose brief includes evaluating a rate rise, and the point of that is residents being able to follow the spend. A report that says both nothing and about 70 per cent of $300,000 does not do that job, and the 21 October meeting is the obvious place to say which is right and what the figure covers. The bigger question is the draft. Councillors were shown Ernst & Young's draft findings in August and the council is already reviewing opportunities the draft identified; the papers promise residents the final report, not the draft, as the council consults on the path forward. The October report says the full final report will be tabled. The least that should mean is that it appears in full in the public business paper, not behind a summary or in a closed session.
We will check the 21 October minutes, which reproduce the report as tabled, and report whether the figure changed or the council explained it.
Update, 22 October 2026: the papers were renumbered, and the minutes are not out yet
The council has reissued the 21 October business paper with its items renumbered. The report this story is about is now item 9.3.8. We downloaded it again on 22 October and its text is the same as the item 8.3.8 we first read, word for word, both expenditure sentences included. The meeting was held on 21 October. Its minutes were not on the council’s Minutes and Agendas page when we checked early on 22 October, so we cannot yet say what councillors were told or what they resolved. The check promised above stands.
How we sourced this
Everything here is from two Bathurst Regional Council documents: item 8.3.8 (now 9.3.8) of the business paper for the 21 October 2026 ordinary meeting (2 pages), and item 8.3.7 of the minutes of the 16 September 2026 ordinary meeting (pages 122 and 123 of the minutes, and its resolution ORD2026-252 on page 124). We read both in full on 18 October 2026. Everything about the review is from those two documents; the quoted February resolution is as both reports set it out, and it matches the minutes of the 18 February meeting, which we read on 21 October 2026 along with the general manager’s report in them. The special rate variation explanation is general background, the accounts figures are from our 8 October story, and the $210,000 is our arithmetic on the council's percentage.
What we have not done. We have not seen Ernst & Young's draft or the scope of works, which the February resolution required be provided to councillors, and we have not asked the council which expenditure figure is correct. The October paper is an agenda; what the council resolves on 21 October may differ.
Sources
Made like this: AI did the reading and drafting, people carry the responsibility, working from the primary sources below. Before it ran, a script matched 14 quotations letter for letter against our saved copies. More on our method.
- Bathurst Regional Council, Agenda, Ordinary Meeting 21 October 2026, item 9.3.8 Financial Sustainability Strategy: Beyond 2026 - Update (PDF, 2 pages, read 18 October 2026 as item 8.3.8 and again on 22 October 2026 as renumbered): the February resolution and its status, the two expenditure statements (page 2), the November timing and the carry-over.
- Bathurst Regional Council, Minutes, Ordinary Meeting 16 September 2026 (PDF, 180 pages, item 8.3.7 on pages 122 and 123 and resolution ORD2026-252 on page 124, read 18 October 2026): the 24 August councillor briefing on the draft findings, the September expenditure statements and resolution ORD2026-252.
- Bathurst Regional Council, Minutes, Ordinary Meeting 18 February 2026 (PDF, 352 pages, item 8.1.1 Financial Sustainability Strategy: Beyond 2026 with the general manager’s report, and resolution ORD2026-31 on pages 40 to 43, read 21 October 2026): the officer recommendation, the $300,000 GST exclusive, the amendments and divisions, and the resolution as carried.
- Bathurst Regional Council, Minutes of the Ordinary Meeting of Council, 21 October 2026, item 9.3.8, Financial Sustainability Strategy: Beyond 2026 - Update (PDF, pages 126 to 128, read 23 October 2026): the report as tabled, with both expenditure statements, and resolution ORD2026-283 with its division.
- Bathurst Regional Council, Agenda, Ordinary Meeting 18 November 2026, item 9.2.13 Financial Sustainability Strategy: Beyond 2026 - Update (PDF, 2 pages, read 13 November 2026): the single expenditure figure, the final report's status and the recommendation.
Work for the council, or read the papers differently? Tell us and we will check it against the documents and log the outcome here.