What is being built
Health Infrastructure, the NSW Health agency that plans and delivers public hospital building projects, put a Review of Environmental Factors for the Forbes Hospital Operating Theatre project on public exhibition on Friday 20 November. A Review of Environmental Factors is the planning report a government agency prepares when it can approve its own project; for this one Health Infrastructure is both the proponent and the body that decides it. The project is the one the NSW Government funded in its 2025-26 Budget.
The report (page 4) describes a new operating theatre unit with one full standard-sized operating theatre, one anaesthetic induction room, and rooms for consultation, booking, recovery, cleaning, storage, deliveries and staff. To make room, the hospital’s single-storey Education and Training Conference Building, called Building H, would be demolished. The new unit is a single-storey extension of the main hospital building, about 7 metres high at its tallest, facing Berkley Street. The old theatre would then be refitted as the education and training space, so the two uses swap places.
- Cost
- $20.2 million, committed in the 2025-26 NSW Budget
- Theatres
- One standard operating room (60 m²), replacing the one existing theatre
- Model
- Day only surgery; operating hours 7am to 6pm, three to five days a week
- Floor area
- 698 m² new; 270 m² demolished (Building H); 428 m² net gain
- Staff
- Theatre staff from 6.57 to 11.05 full-time equivalent, an increase of 4.48
- Timing
- Demolition and main works from early 2027; operating in the first quarter of 2028
- Comment by
- 11.59pm Friday 18 December 2026
Why the old theatre has to go
The case is set out in the Architectural Design Statement by Fulton Trotter, the
project’s architects, which is exhibited with the report. It says the existing theatre
was built in 1969, partly refurbished in 2005, and no longer meets contemporary clinical
standards. Its dimensions do not comply with the Australasian Health Facility Guidelines,
the planning standard used for Australian hospitals,
with insufficient area to accommodate laparoscopic equipment and modern surgical workflows.
A
It is also poorly placed in relation to the emergency department, maternity, medical
imaging and the inpatient ward, and is reached by a public corridor, which the statement
calls not ideal for emergency procedures.
Exhibit A · from the source
Forbes Hospital is part of the Lachlan Health Service, which groups it with Parkes
Hospital 33 kilometres away, within the Western NSW Local Health District, the public health
service for the region. The report (page 8) says there is one theatre at Forbes and two at
Parkes, and that
After hours emergency surgery cover is provided at Forbes operating theatre only (due to workforce availability).
The Forbes theatre is the only surgical service in the Forbes community and one third of
the Lachlan Health Service’s theatre space, and there is no private surgical facility
in the catchment.
The design statement lists what the new unit is meant to make possible. First on the
list is
Recommencement of laparoscopic surgery at Forbes Hospital.
B
The others are making Forbes a district-wide specialty ophthalmology (eye surgery) hub, and
adding minor day-only orthopaedic and urology procedures. It plans the unit as a day only
surgery service and says
Operating hours are scheduled from 07:00 to 18:00, three to five days per week.
Exhibit B · from the source
On demand, the same page says that as at March 2025, 417 patients were waiting for
elective surgery, with baseline activity of 1,306 cases in 2023/24; it gives those figures in
a paragraph about the whole Lachlan Health Service catchment of Forbes, Lachlan and Parkes.
When the money was announced in June 2025, the Member for Orange, Phil Donato, said in the
Health Minister’s release that
more than 770 procedures have been performed in the last financial year
at Forbes.
What happens while it is built
The report (page 36) plans three stages: demolish Building H and do the enabling works;
build the new unit; then fit out the old theatre for education and training. The existing
theatre stays open until the new one is commissioned, so
A temporary operating theatre is therefore not required
,
which the report calls the main advantage over refurbishing the old theatre in place.
The timetable (page 38) has demolition and main works starting in the first quarter of
2027, main works finished in the last quarter of 2027, and commissioning and operation in
the first quarter of 2028, after about 12 months of construction in standard hours (7am to
6pm weekdays, 8am to 1pm Saturdays).
For neighbours, the report (page 61) says that in the worst-case 15-minute period, construction noise is predicted to go over the noise management levels at the nearest homes, particularly those to the south across Berkley Street, though below the 75 dBA “highly affected” level. Twelve staff and fleet parking spaces next to Building H go, cutting the site’s off-street spaces from 33 to 21 (page 41); the report says on-street parking nearby can absorb that and the expected rise of five spaces in peak demand. A council-approved construction zone on Berkley Street could also take about 12 on-street spaces while the work runs (page 39).
The building that comes down
Building H is older than it looks. The heritage assessment by OzArk, summarised in the
report (pages 70 and 71), says it is highly likely to stand where Forbes’s brick hospital
was built in 1876, served as an isolation ward from at least 1877 to 1954, was remodelled
as the maternity wing until the 1990s, and was largely rebuilt around 1937. It is not itself
listed: the hospital’s heritage listing centres on the 1901 McClean Wing on Elgin
Street and the mortuary. OzArk rates the building’s authenticity and integrity low and
finds that demolition is
a total loss of heritage value to Building H
but has a negligible effect on the wider hospital listing. Its recommendations are a
photographic record before demolition, shared with Forbes Shire Council and Forbes Library;
interpretive signage prepared with the Forbes and District Historical Society; and reuse of
the timber windows and bricks, or their offer to a local salvage yard.
How to have your say
The report and its appendices are on the NSW Government’s Have your say page for the project, which takes submissions until 11.59pm on Friday 18 December 2026. The project team will be at drop-in sessions near the hospital’s main entrance on Monday 7 December, 11am to 1pm, and Tuesday 15 December, 2pm to 4pm. Questions go to the project team on 9978 5432 or HI-Info@health.nsw.gov.au. Health Infrastructure says submissions will be answered in a Response to Submissions Report and used to finalise the design before construction.
Our view
This is opinion, built on the facts above. The case for a new room is made plainly and is convincing. A theatre too small for laparoscopic equipment cannot offer the keyhole operations that are now routine, and the report says it is where the Lachlan Health Service’s after-hours emergency surgery is done. Building the new unit next door while the old one keeps working, rather than closing it for a refit, is the right call for a town with one theatre.
What the exhibited papers do not do is say what the $20.2 million buys in operations.
It is still one theatre. It is planned to run three to five days a week, and the papers do not say which
end of that range it will open at. The only daily figure we found in the text of the report and
its appendices is in the services engineer’s water estimate, which assumes
approximately five theatre procedures per day
(page 11). The waiting list figure is from March 2025. A resident writing a submission is
entitled to know how many more operations Forbes can expect.
The record of what the community has said so far is also thin. The report calls the
engagement extensive, but the engagement report exhibited with it is marked Draft, lists
two staff and community drop-in sessions, one with Yoorana Gunya Family Healing Centre and
a council briefing without recording what anyone raised, and still gives the public
exhibition as expected in
Late 2027
.C
The two December drop-ins are the chance to put questions on the record.
Exhibit C · from the source
We asked Health Infrastructure on 26 November how many operations a year the new theatre is planned to perform, on how many days a week it will run when it opens, and whether a corrected engagement report will be published. We will publish its answer as given, or say if none arrives.