What councillors endorsed
Mid-Western Regional Council, the council for Mudgee, Gulgong and Rylstone, has been planning the Mortimer Street Precinct since March 2024, when a staff report described the site as vacant land behind the Mortimer Street complex, zoned E2 Commercial Centre. The planning and design work is paid for by $2 million from the Australian Government’s Regional Precincts and Partnerships Program and $500,000 from the council.
Report 9.8 to the 18 November meeting asked councillors to endorse the revised concept
as the preferred basis for progressing detailed design
.
It describes the scheme this way:
The current concept includes a two-storey building addressing Church Street and buildings of up to four storeys further within the precinct. The indicative residential yield is approximately 44 apartments
,
subject to refinement. The concept design attached to the report, dated 6 November,
counts 41 in its yield table (24 in Building B and 17 in Building C), plus 1,430 square
metres of retail and commercial space across three buildings.
Resolution 278/26, moved by Cr Shelley and seconded by Cr Palmer, adopted the
recommendation unchanged. Eight councillors voted for it.
It is noted that Cr Thompson abstained from voting, which is recorded as a Nay vote.
The resolution also asks for a further report on the detailed design, final business
case, delivery and funding arrangements, and final parking provision.
- Site
- Council land between Mortimer and Church Streets, Mudgee CBD; in the Mudgee Heritage Conservation Area
- Endorsed 18 Nov
- Scheme 01, The Grain, as the basis for detailed design (res 278/26, 8 to 1)
- Homes
- About 44 apartments in the report; 41 in the attached yield table
- Height
- Up to four storeys; above current controls, so a planning proposal comes first
- Parking
- 195 spaces on site, no basement: 109 needed by the new buildings, 86 left for public parking
- Not decided
- Construction, the delivery model, funding, final parking and whether Stage 5 is built
Five stages, and the money favours four
The concept would be built in stages: first move the at-grade parking towards the eastern boundary, then upgrade the Clarke Street connection, then Building A and the plaza, then Building B with extra temporary at-grade parking, and last, Stage 5, Building C and the decked car park.A
The report gives two sets of preliminary figures, rounded to the nearest $1 million.
Stopping after Stage 4: $30 million in estimated sale revenue against $19 million in
construction and site costs, an indicative surplus of $11 million. The full scheme:
$60 million against $40 million, a surplus of $20 million. It warns the surplus
does not represent Council’s net profit or cash flow
,
because it counts sale revenue against construction and site costs only.
Exhibit A · from the source
On current estimates, delivery through Stage 4 offers a higher indicative margin (38% of revenue compared with 33% for the full scheme) and defers approximately $21 million in expenditure, including $6 million for the decked car park.
The recommended scheme includes building heights above the current planning controls for the site.
Our arithmetic on the rounded figures: $11 million of $30 million is about 37%, and
$20 million of $60 million is about 33%; the report’s 38% presumably comes from the
unrounded estimates. The $21 million deferred matches $40 million less $19 million. The
report says stopping at Stage 4
would allow Council to assess residential and parking demand before deciding whether and when to proceed with Stage 5.
The planning rules and the deadline
Because the buildings are taller than the current controls allow, the council must prepare and lodge a planning proposal to change the height limit before a development application can go in. An extract from the draft Mudgee Town Centre Growth Strategy, reproduced in the concept design (page 168), says the maximum building height in the town centre is now 8.5 metres and suggests up to 15 metres, four storeys, in strategic, less visible locations.
The grant clock is tight. The council has asked the program for a six-month extension.
If the extension is not approved, Council will need to shorten the remaining project consultation periods to work towards the existing 31 March 2027 deadline for lodgement of the Development Application.
The report adds that the planning proposal
also puts that deadline at risk.
What residents asked for, and what the parking money bought
The council’s Your Say page says a survey in February drew 690 responses,
with residents highlighting a desire for accessible, undercover parking, along with spaces for retail, health, specialist and allied health services.
Three drop-in sessions on 4 and 5 November drew 42 people, the report says. The concept
has no basement parking; its only parking structure is the decked car park in Stage 5.
The site’s parking history sits in the same business paper. Answering a
question from Cr Thompson about the development parking contributions fund (item 6.6),
staff list car-parking spending over 15 years: $1.2 million on “Land Mortimer and
Church St” in 2009/10, and $573,979 on “Mortimer St Carpark Development”
across 2010/11 to 2012/13 ($1,810 plus $562,169 plus $10,000, our addition). The car
parking fund held $230,000 at 30 June 2026, and
Over the past 15 Years, Council has receipted only one contribution towards parking in 2011/12 for $340,377.
Our view
This is opinion, built on the facts above. Putting homes and shops on a vacant patch of the CBD is a reasonable ambition, and building in stages, so the council can test demand before it commits to the last and costliest piece, is the prudent way to do it. The report is candid that its figures are rough and that the surplus is not profit.
But the staging runs in the opposite order to what residents asked for. The one
parking structure is in Stage 5, the stage the council’s own numbers make easiest
to drop. And the council’s own table records car-parking contributions spent on
“Land Mortimer and Church St” and on a Mortimer Street car park. So the business case
should set out the parking ledger in plain numbers: how many public spaces the site
gives now, how many at each stage, and how many if Stage 5 never comes. The report
already says the final proposal must explain
any change from Council’s earlier parking baseline
,
but the papers do not give that baseline. We asked Mid-Western Regional Council on
21 November how many public car spaces the site provides today, and how many would
remain public at the end of Stage 4 if Stage 5 is deferred. We will publish its answer
as given, or say if none arrives.