Mid-Western council sets out its terms for data centres: no town water or groundwater for routine cooling, new power to match their demand, and preferably 5 km from towns

On Wednesday 21 October Mid-Western Regional Council voted unanimously to put a draft position on data centres out for comment. It would not support data centres that cool with town water or groundwater as a matter of routine. It wants large ones to underwrite new generation and firming at least equal to their demand, and it prefers them outside 5 kilometres of Mudgee, Gulgong, Kandos, Rylstone and the villages. The paper is not a planning control, and the biggest projects would be decided by the state. Submissions closed at 4.30pm on Friday 20 November.

Why a council is writing rules for something nobody has proposed

Neither the paper nor the staff report names a data centre proposed for the region. The report says the paper is meant to give the council a clear position before individual proposals become advanced. The reason it gives is the Central-West Orana Renewable Energy Zone: the region sits inside it, near new electricity infrastructure, and the paper says that may draw more interest from data centre builders. As at August 2026, it says, the council was engaging with more than 55 renewable energy projects in and around the local government area.

The paper sets out the scale it is responding to. It cites NSW figures that data centres are seeking up to 28 GW of network connection capacity, with around 13 GW in advanced discussions, more than the state’s average electricity demand, and that 20 data centre projects worth about $51.4 billion are in the State Significant Development pipeline. It also notes National Cabinet’s agreement on 26 August 2026 to develop mandatory national minimum requirements for large data centres covering energy, water and land use, with legislation proposed for early 2027. Its summary puts the council’s stance this way: Council supports the opportunity in principle, but not at any cost.

What it would and would not support

  • Water. Routine cooling should not rely on potable town water or groundwater extraction. The paper prefers waterless, closed-loop, dry, hybrid, recycled-water and stormwater cooling, and asks proponents for peak-day water demand, not only annual averages, because peak cooling can coincide with heatwaves and drought. It says closeness to council water and sewer mains does not constitute confirmation that servicing capacity is available to a development.
  • Electricity. Large data centres should underwrite new renewable generation and firming equal to or greater than their demand, pay their connection costs, take part in demand response, and not raise prices or reduce reliability for existing users.
  • Location. A general preference for major data centres outside a five-kilometre radius of towns, villages, urban release areas and identified growth areas. The paper says this is not an absolute exclusion: the council could back a site inside it through its own strategic or precinct planning, but not through one-off exceptions sought by a developer.
  • Farmland. Avoid agricultural land of strategic value, including mapped Biophysical Strategic Agricultural Land and high Land and Soil Capability land, where reasonable alternatives exist.
  • Costs. Proponents pay the full direct and lifecycle cost of the roads, water, wastewater and other infrastructure their project generates.
  • Community benefit. A separate Data Centre Planning Agreements Policy, drawing on the council’s renewable energy planning agreements policy. The paper lists four ways a contribution could be charged (per megawatt, as a share of capital value, as an annual payment, or a mix) and says no rate should be set until those are tested.
  • Cumulative impact. Assess any data centre against the whole REZ and major-project pipeline affecting the region, including projects outside the council’s boundary.

What it is not

The paper says it does not amend the local environmental plan or development control plan, create development rights, bind a consent authority or replace merit assessment. Data centres above the State Significant Development threshold are assessed by the NSW Department of Planning, Housing and Infrastructure, so for the largest projects the council would not be the decision-maker. The paper says it would use the position to frame submissions, argue for assessment requirements and conditions, and negotiate planning agreements.

The resolution, number 235/26, moved by Cr Pryor and seconded by Cr Dicker, puts the paper on exhibition for 28 days and asks for a further report after it closes, covering the submissions, any material state or Commonwealth policy changes, and a final paper for adoption. The report says exhibition costs come from existing budgets; the technical studies, precinct work and planning agreements policy the paper calls for would go through separate budget and council processes.

How to comment

The paper is on the council’s documents on exhibition page, which has a feedback form, and at its customer service centres. The page says written submissions must be addressed to the General Manager and received before 4.30pm on Friday 20 November 2026.

Our view

This is opinion, built on the facts above. Writing the terms before anyone asks is the right order. Once a site is bought and a connection agreed, a council’s leverage shrinks to a submission. The water position is the strongest part: ruling out routine town water and groundwater, and asking for peak-day rather than average demand, targets the risk a dry inland region carries, and the warning that a nearby main is not spare capacity is the kind of line a proponent’s summary tends to skip.

The limits are as plain. For the projects big enough to matter, the state decides, and the paper binds nobody, so its force depends on whether the department writes these terms into conditions. The five-kilometre preference has a door in it, deliberately; whether that door stays council-led is a test for the first real proposal. And a community benefit with no rate is still a promise to negotiate. The next useful step is the technical work the paper itself lists, which has no budget yet.

Update, 21 November 2026: the exhibition has closed

Submissions closed at 4.30pm on Friday 20 November. We changed “close” to “closed” in the description, the standfirst and the cards; nothing else on this page changed. The next step is the further report on submissions that resolution 235/26 asks for.

We will report what the council adopts after the exhibition closes, and any change from this draft.

How we sourced this

We read the exhibited draft Data Centres and Digital Infrastructure Interim Position Paper (32 pages) in full, item 8.7 of the business paper for Mid-Western Regional Council’s ordinary meeting of 21 October 2026 (the staff report), and resolution 235/26 in the unconfirmed minutes of that meeting, all on 29 October 2026. The national and state figures are as the paper reports them, citing its own references; we have not checked each against its original. We searched the paper and the report for any named or lodged data centre proposal in the region and found none. We have not contacted the council. The section headed Our view is opinion.

Sources

Made like this: AI did the reading and drafting, people carry the responsibility, working from the primary sources below. Before it ran, a script matched 4 quotations letter for letter against our saved copies. More on our method.

  1. Mid-Western Regional Council, Data Centres and Digital Infrastructure Interim Position Paper, October 2026 (PDF, 32 pages, exhibition draft, read 29 October 2026): the executive summary and proposed positions, the strategic context (sections 2.1 to 2.3), the headline position and the list of proposals the council does not support (section 3), water and groundwater (5.1, 5.2), location and town buffers (5.4) and the planning agreement contribution models (7.3).
  2. Mid-Western Regional Council, Business paper, ordinary meeting of 21 October 2026, item 8.7 (PDF, read 29 October 2026): the report by the Director Development, the key policy directions table, the five-kilometre separation, financial implications and associated risks.
  3. Mid-Western Regional Council, Unconfirmed minutes, ordinary meeting of 21 October 2026 (PDF, read 29 October 2026): item 8.7, resolution 235/26, carried unanimously. The exhibition page gives the closing time.

Live near a proposed site, or read the paper differently? Tell us and we will check it against the documents and log the outcome here.