How to have your say
Submissions go through the
project's page on the NSW Planning Portal
(application SSD-109430741), where the environmental impact statement and its appendices
can be read. The exhibition notice is direct about the channel:
To have your say on this project, you must lodge a submission online through the NSW Planning Portal before the close of exhibition.
- Closes
- Thursday 17 December 2026 (exhibition opened Thursday 5 November)
- Decides
- The Independent Planning Commission, as delegate for the Minister for Planning and Public Spaces
- A submission needs
- A declaration of any reportable political donations you have made in the last two years. You can ask for your name to be withheld from the published list of submitters
- Public hearing
- None directed when the notice was published, the notice says
- Help
- Planning Portal help line 1300 305 695; project enquiries 02 9274 6431
What is proposed
The applicant is The Trustee for Parkes Energy Recovery Project Trust, on land at 545,
664 and 747 Nelungaloo Road. The notice describes a facility
with a capacity to thermally treat up to 732,000 tonnes per annum of residual waste for the purpose of generating up to 80 megawatts of energy
,
with ash management, a visitor education centre, offices, water and transmission
infrastructure and internal roads.
The figures below are the proponent's, from its environmental impact statement dated October 2026. None has yet been tested by the agencies that will review it.
| Item | The EIS says | PDF page |
|---|---|---|
| Where the waste comes from | Mostly Greater Sydney, a smaller amount from Parkes and surrounding council areas | 4 |
| How it arrives | Mostly by rail, transferred from the proposed Parkes Intermodal Terminal on internal roads | 21 |
| Electricity | About 70 to 80 MW generated, about 65 MW exported; the EIS equates this to the annual needs of about 100,000 homes | 14 |
| Stacks | Flue gas stacks about 60 m high | 121 |
| Nearest occupied home | About 1.4 km west when construction starts; a home about 1 km south is on a short-term lease and would be vacated first | 67 |
| Construction | About 48 months, a peak workforce of up to 400, about $948 million | 21, 84 |
| Jobs once running | About 313 full-time equivalent ongoing jobs supported, including 50 direct on-site roles | 14 |
| Planning agreement | Over $1.22 million a year over a 40-year life, about $100 million with indexation | 84 |
On the stated need, the EIS argues that
Greater Sydney is facing a growing mismatch between the amount of residual waste generated and the capacity available to manage it.
The project was declared state significant development on 13 March 2026, the declaration
amended on 19 October; the environmental assessment requirements were issued on 17 March
and amended on 20 October.
What the committee found
The Legislative Council's Select Committee on Proposed Energy from Waste Facilities, chaired by Nichole Overall of the Nationals, tabled its first report on 20 October. Its media release says the inquiry received more than 1,400 submissions and held five public hearings and two public forums, in Parkes and Goulburn-Mulwaree. It made 22 recommendations. Two bear directly on Parkes.
That the NSW Government not proceed with approval of the current proposed regional New South Wales waste-to-energy facilities in the absence of numerous critical elements, but most significantly, the absence of conclusive social licence and community acceptance, including from local councils and Aboriginal Land Councils.
Recommendation 7 asks the Government to
impose a moratorium on all current waste-to-energy proposals
and commission an independent review of the designated precincts and how they were
chosen. Among its findings: the Parkes and Goulburn Mulwaree proposals would be the first of
their kind on the eastern seaboard; there is strong and sustained regional opposition; and
such plants have operational lifespans of 25 to 30 years while the Parkes proponent is
seeking a 40-year lease.
The committee was split. Its minutes record that Emily Suvaal moved to delete the
moratorium recommendation; she, Sarah Kaine and Peter Primrose, the three Labor members,
voted for that, and four members voted against. In her dissenting statement Ms Suvaal
wrote that
it is not viable to suggest a moratorium on Energy from Waste without providing clear alternatives to manage NSW's residual waste needs
,
and that
Some energy from waste facilities will be required in NSW.
The Greens' Amanda Cohn dissented the other way: the report, she wrote, falls short by not
recommending that the Government
extend the existing prohibition on waste-to-energy incineration in Greater Sydney to apply across all of New South Wales.
Parkes Shire Council heard about the report the day it was tabled. The minutes of its
20 October meeting record the Mayor advising councillors of its release, and a resolution
in closed session that council
Will not make a decision about engaging an independent consultant, until further clarification of developments contained in the report
.
- 13 March 2026Declared state significant development (amended 19 October).
- 17 March 2026Environmental assessment requirements issued (amended 20 October).
- 20 October 2026Select committee tables Report 1: 22 recommendations, including no approval without conclusive social licence.
- 5 November 2026EIS goes on public exhibition.
- 17 December 2026Submissions close. The Independent Planning Commission decides after the assessment.
Our view
This is opinion, built on the facts above. A committee recommendation is advice, not law, and this one came with the governing party's own members voting against its moratorium. Nothing in it stops the assessment, and the exhibition is running on its normal clock. For anyone in Parkes with a view either way, that makes the next six weeks the part that counts: a Planning Portal submission is the one channel the exhibition notice names, and the committee's report is not a substitute for it.
The EIS is long and its central claims, on air quality, health risk and traffic, are the proponent's own. The useful submissions will be the ones that engage with them: whether a home 1.4 km away and stacks 60 m high are acceptable, whether rail delivery of Sydney's waste is locked in, and whether a 40-year life fits plants the committee found run 25 to 30. We will report what the agencies say in their responses when they are published.