Update, 21 November 2026: councillors adopted all four motions

The unconfirmed minutes of the 18 November meeting (pages 3 to 6) record that councillors adopted Cr Pryor’s four motions together, moved by Cr Pryor and seconded by Cr Lang, in place of the staff recommendations against writing again. Each was carried 6 to 2, with Cr Cornish and Cr Palmer voting against. Cr Shelley declared a pecuniary conflict of interest, as he is employed part-time by Bowdens Silver, and left the chamber for the four items.

Resolution 264/26 reaffirms the council’s 13 October request, asks the commission to have Bowdens make an updated offer to vary the planning agreement on the current capital cost before the application is determined, with any consent requiring the varied agreement before construction, and authorises the General Manager to begin negotiations with Bowdens on the variation. Resolutions 265/26 to 267/26 ask the commission to keep the word “avoid” in condition B89(c), to set numeric lead limits with baseline testing, independent monitoring, trigger levels and public reporting, and to obtain the written advice of the NSW water agencies on the groundwater request before it decides. The minutes are unconfirmed until the council’s next meeting. Nothing else on this page changed; the commission’s determination is the next thing we will report.

Where the mine is up to

Bowdens Silver wants to build an open-cut silver, lead and zinc mine at Lue, east of Mudgee. The Independent Planning Commission approved it in April 2023. Its case page now says that consent has been declared void by the Court. So the commission is deciding the application again, with a new round of material from the company and the Department of Planning, Housing and Infrastructure. It held a public hearing in Mudgee from 14 to 16 October 2026, and written submissions closed at 11.59pm on 11 November after two extensions. No decision has been published.

What the 2022 agreement pays

A voluntary planning agreement is a deed in which a developer promises money or works to a council in return for the development going ahead. Bowdens says its agreement with Mid-Western was executed in March 2022. The draft the council put on exhibition in October 2021 sets the sums by formula. It defines the initial capital cost, or ICC, as a figure that means the initial capital cost of the Development totalling $246 million (with 1% of the ICC being $2.46 million).A On top of that it pays 1% of $54 million in later additional annual capital expenditure ($540,000) and $1,705,000 towards maintaining Lue Road and nearby roads, paid in instalments over about 15 years of production, with every payment adjusted for the Consumer Price Index.

Exhibit A · from the source

From the definitions in the draft Voluntary Planning Agreement for Bowdens Silver Mine, exhibited October 2021: ICC means the initial capital cost of the Development totalling $246 million, with 1% of the ICC being $2.46 million.
PDF page 5 of the draft Voluntary Planning Agreement for Bowdens Silver Mine, as Mid-Western Regional Council exhibited it in October 2021 (the grey watermark is the draft's own), read 17 November 2026. Outlined: the defined initial capital cost and the 1% of it. Bowdens' October 2026 letter gives the executed agreement's total as about $4.7 million, the same sum as this draft's figures. Open the draft agreement Back to the story

What the mine now costs to build

Bowdens Silver is owned by the ASX-listed Silver Mines Limited. Its Definitive Feasibility Study, announced to the market on 21 July 2026, says Initial capital costs are estimated at A$455mB for the first stage, 37% above its December 2024 study. The company puts most of the rise down to mining cost inflation of 10 to 15% a year and extra filtered-tailings works. Against the $246 million in the agreement, $455 million is 85% higher (our arithmetic). The same study's table puts first-stage sustaining capital at A$23.5 million, and A$90.8 million over a 26-year life that includes a second stage it describes as subject to approvals.

Exhibit B · from the source

From Silver Mines Limited's ASX announcement of 21 July 2026 on the Bowdens Definitive Feasibility Study: initial capital costs are estimated at A$455m.
Page 1 of Silver Mines Limited's ASX announcement of 21 July 2026, Bowdens Definitive Feasibility Study Confirms Robust Economics as Reserves Lift to 93.5M Oz of Silver, read 17 November 2026. Outlined: the initial capital estimate. Open the announcement Back to the story

The mine's estimated value to the state has grown much faster. The department's supplementary advice to the commission, of September 2026, reports an updated economic assessment that puts the net production benefit (net social benefit) to NSW would now be $341 M instead of $44 M, and royalties to the NSW Government would be $58 M instead of $21 M.

Initial capital cost in the agreement
$246 million; 1% is $2.46 million
Initial capital, July 2026 study
A$455 million (stage 1), 85% higher
Agreement total, as signed
About $4.7 million: the 1% of initial capital, $540,000 on later capital, $1.705 million for roads
Agreement total with CPI, per Bowdens
About $5.7 million
With the 1% on $455 million
$6.795 million before CPI, in the motion's table
Net benefit to NSW, department's advice
$341 million, up from $44 million

What the council has asked, and what Bowdens said

The council raised it with the commission on 28 September. Alina Azar, speaking for the council, told the panel There is a change to the capital cost to the project that isn’t currently reflected in the VPA. Asked to put a number on it, she said the community infrastructure money in theory would move from $3 million to $5 million. The council's staff say it then wrote to Bowdens on 7 October asking to negotiate, and repeated the request in a submission to the commission on 13 October.

At the hearing on 14 October, commissioner Richard Pearson asked Bowdens' Jo Battershill whether the company proposed to increase the agreement, given the increased value of the resource as per your presentation? He answered: The VPA is already agreed. We’ve already discussed with Council that there is an opportunity to open that up.

The commission followed up in writing. Bowdens' reply of 28 October says that with the agreement's CPI adjustment, the payments have increased to approximately $5.7 million. It concludes that no additional conditions are considered necessary in relation to the VPA.C It adds that Bowdens Silver has informed Council that it is willing to engage in discussions with Council regarding the existing VPA terms.

Exhibit C · from the source

From Bowdens Silver's letter to the Independent Planning Commission of 28 October 2026: with CPI the agreement's payments have increased to approximately $5.7 million; no additional conditions are considered necessary in relation to the VPA; Bowdens is willing to engage in discussions with Council on the existing terms.
PDF page 3 of Bowdens Silver's letter of 28 October 2026 to the Independent Planning Commission, responding to questions on notice (published on the commission's case page as received 29 October), read 17 November 2026. Outlined: the CPI-adjusted total and the company's view that no further condition is needed. Open the letter Back to the story

The motion, and the staff answer

Cr Rod Pryor's motion, item 6.2 in the business paper for 18 November, asks the council to reaffirm its 13 October request, write to the commission asking that Bowdens be invited to make an updated offer before the application is decided, and require any varied agreement to be signed before construction. Its background notes This motion does not ask Council to support or oppose the project. Its table takes the agreement from $4.705 million to $6.795 million before CPI, about $2.1 million more, by swapping $455 million for $246 million and leaving the rest alone. On the CPI answer it says CPI keeps the 2018 figure up to date for inflation; it does not reflect the higher capital cost.

The table keeps the later-capital line at 1% of $54 million. The July 2026 study puts first-stage sustaining capital at A$23.5 million, so rebasing both capital lines on stage one gives $4.55 million plus $0.235 million plus the $1.705 million for roads: about $6.49 million before CPI (our arithmetic). Using the A$90.8 million life-of-mine figure instead gives about $7.16 million, but that includes a second stage not yet approved.

The staff comment does not dispute the arithmetic. It says the council's request is already with Bowdens and the commission, and it reads section 7.7(3) of the Environmental Planning and Assessment Act 1979 as allowing a consent condition requiring a planning agreement only in the terms of an offer the developer has made. So Council’s request for increased contributions does not itself constitute such an offer, and Bowdens' willingness to talk is not an offer either. Staff add that determination does not prevent Council and Bowdens Silver from subsequently negotiating and entering into a voluntary variation. Their bottom line: Any additional contributions remain subject to agreement and should not be presented as secured revenue. They also checked whether a letter now would count, since submissions closed on 11 November. The IPC advised that the Panel is not legally required to accept late submissions and that acceptance is at its discretion.

The other three motions

Cr Pryor has three more on the same agenda, each with a staff recommendation against writing again. Item 6.3 asks the council to hold to its proposed condition that Bowdens use reasonable and feasible measures to keep construction workers out of short-stay accommodation and existing housing. Its wording, quoted in Bowdens' letter, is to propose reasonable and feasible measures to avoid the use of short-stay accommodation or existing housing stock by the construction workforce. Bowdens asks that avoid become minimise, saying a requirement to avoid short-stay accommodation may not be practical at peak construction. Item 6.4 asks for numeric limits on lead in air and deposited dust, baseline testing and published monitoring; staff say the commission has already put detailed questions on lead to the department, informed by the EPA, and that Council has not undertaken an independent specialist assessment that would provide a technical basis for recommending different or additional requirements. Item 6.5 concerns a clause 4.6 request Bowdens lodged on 28 October about the groundwater standard at two high-priority groundwater dependent ecosystems; staff say that is a question of law for the commission. The council's own position on accommodation and notification of air quality exceedances is already before the commission in its 13 October submission.

Our view

This is opinion, built on the facts above. The council has the principle right. The deal was 1% of what the mine costs to build, and $246 million was the estimate of the day, not the bargain. With the company's own study at $455 million and the department's advice putting the net benefit to NSW at $341 million rather than $44 million, paying the region 1% of an out-of-date figure means the share it agreed to has quietly shrunk. CPI does not fix that: it adjusts for inflation, not for a bigger build.

Two cautions. Rebasing on the July 2026 study cuts both ways: on stage one the later-capital line shrinks, so the honest rebased figure is nearer $6.49 million than $6.795 million. And staff are right on the law. On their reading of section 7.7(3), a letter from the council cannot turn into a condition, and a late letter may not even be read.

Which is why the question now sits with Bowdens. Its representative told the hearing there is an opportunity to open that up, and its letter says it is willing to talk. If it means that, the simplest course is to put a written offer on the current capital figure to the commission before it decides, where it can be made a condition. Once consent is granted the council negotiates on goodwill alone. Whatever councillors decide on 18 November, we will report it when the minutes are published, and report what the commission's determination says about the agreement.