Update, 21 November 2026: councillors adopted all four motions
The unconfirmed minutes of the 18 November meeting (pages 3 to 6) record that councillors adopted Cr Pryor’s four motions together, moved by Cr Pryor and seconded by Cr Lang, in place of the staff recommendations against writing again. Each was carried 6 to 2, with Cr Cornish and Cr Palmer voting against. Cr Shelley declared a pecuniary conflict of interest, as he is employed part-time by Bowdens Silver, and left the chamber for the four items.
Resolution 264/26 reaffirms the council’s 13 October request, asks the commission to have Bowdens make an updated offer to vary the planning agreement on the current capital cost before the application is determined, with any consent requiring the varied agreement before construction, and authorises the General Manager to begin negotiations with Bowdens on the variation. Resolutions 265/26 to 267/26 ask the commission to keep the word “avoid” in condition B89(c), to set numeric lead limits with baseline testing, independent monitoring, trigger levels and public reporting, and to obtain the written advice of the NSW water agencies on the groundwater request before it decides. The minutes are unconfirmed until the council’s next meeting. Nothing else on this page changed; the commission’s determination is the next thing we will report.
Where the mine is up to
Bowdens Silver wants to build an open-cut silver, lead and zinc mine at Lue, east of
Mudgee. The Independent Planning Commission approved it in April 2023. Its case page now
says that consent
has been declared void by the Court.
So the commission is deciding the application again, with a new round of material from the
company and the Department of Planning, Housing and Infrastructure. It held a public hearing
in Mudgee from 14 to 16 October 2026, and written submissions closed at 11.59pm on
11 November after two extensions. No decision has been published.
What the 2022 agreement pays
A voluntary planning agreement is a deed in which a developer promises money or works to
a council in return for the development going ahead. Bowdens says its agreement with
Mid-Western was executed in March 2022. The draft the council put on exhibition in October
2021 sets the sums by formula. It defines the initial capital cost, or ICC, as a figure that
means the initial capital cost of the Development totalling $246 million (with 1% of the ICC being $2.46 million).
A
On top of that it pays 1% of $54 million in later
additional annual capital expenditure
($540,000) and $1,705,000 towards maintaining Lue Road and nearby roads, paid in instalments
over about 15 years of production, with every payment adjusted for the Consumer Price
Index.
Exhibit A · from the source
What the mine now costs to build
Bowdens Silver is owned by the ASX-listed Silver Mines Limited. Its Definitive
Feasibility Study, announced to the market on 21 July 2026, says
Initial capital costs are estimated at A$455m
B
for the first stage, 37% above its December 2024 study. The company puts most of the rise
down to mining cost inflation of 10 to 15% a year and extra filtered-tailings works. Against
the $246 million in the agreement, $455 million is 85% higher (our arithmetic). The same
study's table puts first-stage sustaining capital at A$23.5 million, and A$90.8 million
over a 26-year life that includes a second stage it describes as subject to approvals.
Exhibit B · from the source
The mine's estimated value to the state has grown much faster. The department's
supplementary advice to the commission, of September 2026, reports an updated economic
assessment that puts
the net production benefit (net social benefit) to NSW would now be $341 M instead of $44 M
,
and
royalties to the NSW Government would be $58 M instead of $21 M
.
- Initial capital cost in the agreement
- $246 million; 1% is $2.46 million
- Initial capital, July 2026 study
- A$455 million (stage 1), 85% higher
- Agreement total, as signed
- About $4.7 million: the 1% of initial capital, $540,000 on later capital, $1.705 million for roads
- Agreement total with CPI, per Bowdens
- About $5.7 million
- With the 1% on $455 million
- $6.795 million before CPI, in the motion's table
- Net benefit to NSW, department's advice
- $341 million, up from $44 million
What the council has asked, and what Bowdens said
The council raised it with the commission on 28 September. Alina Azar, speaking for the
council, told the panel
There is a change to the capital cost to the project that isn’t currently reflected in the VPA.
Asked to put a number on it, she said the community infrastructure money
in theory would move from $3 million to $5 million
.
The council's staff say it then wrote to Bowdens on 7 October asking to negotiate, and
repeated the request in a submission to the commission on 13 October.
At the hearing on 14 October, commissioner Richard Pearson asked Bowdens' Jo Battershill
whether the company proposed to increase the agreement,
given the increased value of the resource as per your presentation?
He answered:
The VPA is already agreed. We’ve already discussed with Council that there is an opportunity to open that up.
The commission followed up in writing. Bowdens' reply of 28 October says that with the
agreement's CPI adjustment, the payments
have increased to approximately $5.7 million.
It concludes that
no additional conditions are considered necessary in relation to the VPA.
C
It adds that
Bowdens Silver has informed Council that it is willing to engage in discussions with Council regarding the existing VPA terms.
Exhibit C · from the source
The motion, and the staff answer
Cr Rod Pryor's motion, item 6.2 in the business paper for 18 November, asks the council
to reaffirm its 13 October request, write to the commission asking that Bowdens be invited
to make an updated offer before the application is decided, and require any varied
agreement to be signed before construction. Its background notes
This motion does not ask Council to support or oppose the project.
Its table takes the agreement from $4.705 million to $6.795 million before CPI, about
$2.1 million more, by swapping $455 million for $246 million and leaving the rest alone. On
the CPI answer it says
CPI keeps the 2018 figure up to date for inflation; it does not reflect the higher capital cost.
The table keeps the later-capital line at 1% of $54 million. The July 2026 study puts first-stage sustaining capital at A$23.5 million, so rebasing both capital lines on stage one gives $4.55 million plus $0.235 million plus the $1.705 million for roads: about $6.49 million before CPI (our arithmetic). Using the A$90.8 million life-of-mine figure instead gives about $7.16 million, but that includes a second stage not yet approved.
The staff comment does not dispute the arithmetic. It says the council's request is
already with Bowdens and the commission, and it reads section 7.7(3) of the Environmental
Planning and Assessment Act 1979 as allowing a consent condition requiring a planning
agreement only in the terms of an offer the developer has made. So
Council’s request for increased contributions does not itself constitute such an offer
,
and Bowdens' willingness to talk is not an offer either. Staff add that
determination does not prevent Council and Bowdens Silver from subsequently negotiating and entering into a voluntary variation.
Their bottom line:
Any additional contributions remain subject to agreement and should not be presented as secured revenue.
They also checked whether a letter now would count, since submissions closed on
11 November.
The IPC advised that the Panel is not legally required to accept late submissions and that acceptance is at its discretion.
The other three motions
Cr Pryor has three more on the same agenda, each with a staff recommendation against
writing again. Item 6.3 asks the council to hold to its proposed condition that Bowdens use
reasonable and feasible measures to keep construction workers out of short-stay
accommodation and existing housing. Its wording, quoted in Bowdens' letter, is to
propose reasonable and feasible measures to avoid the use of short-stay accommodation or existing housing stock by the construction workforce
.
Bowdens asks that avoid become minimise, saying a requirement to avoid
short-stay accommodation may not be practical at peak construction. Item 6.4 asks for numeric limits
on lead in air and deposited dust, baseline testing and published monitoring; staff say the
commission has already put detailed questions on lead to the department, informed by the
EPA, and that
Council has not undertaken an independent specialist assessment that would provide a technical basis for recommending different or additional requirements.
Item 6.5 concerns a clause 4.6 request Bowdens lodged on 28 October about the groundwater
standard at two high-priority groundwater dependent ecosystems; staff say that is a
question of law for the commission. The council's own position on accommodation and
notification of air quality exceedances is already before the commission in its 13 October
submission.
Our view
This is opinion, built on the facts above. The council has the principle right. The deal was 1% of what the mine costs to build, and $246 million was the estimate of the day, not the bargain. With the company's own study at $455 million and the department's advice putting the net benefit to NSW at $341 million rather than $44 million, paying the region 1% of an out-of-date figure means the share it agreed to has quietly shrunk. CPI does not fix that: it adjusts for inflation, not for a bigger build.
Two cautions. Rebasing on the July 2026 study cuts both ways: on stage one the later-capital line shrinks, so the honest rebased figure is nearer $6.49 million than $6.795 million. And staff are right on the law. On their reading of section 7.7(3), a letter from the council cannot turn into a condition, and a late letter may not even be read.
Which is why the question now sits with Bowdens. Its representative told the hearing
there is
an opportunity to open that up
, and its letter says it is willing to talk. If it
means that, the simplest course is to put a written offer on the current capital figure to
the commission before it decides, where it can be made a condition. Once consent is granted
the council negotiates on goodwill alone. Whatever councillors decide on 18 November, we will
report it when the minutes are published, and report what the commission's determination
says about the agreement.